Photo/rendering of Camp Creek Water Reclamation Project

Camp Creek Water Reclamation Project

Hawkins served as special procurement and contract counsel to Fulton County for its new 24 mgd Camp Creek Wastewater Treatment Plant. The contractor's workscope included building a new and larger treatment plant to meet more stringent renewal permit standards while operating an existing aging facility. Hawkins substantially assisted in RFP development, and drafted and negotiated the DBOM contract.

Client Fulton County, Georgia
Role Owner's Lead Counsel
Distinction Georgia's First Major Water Sector Alternative Delivery Project
Delivery Method Design-Build-Operate-Maintain
Project Size 24 MGD
Capital Cost $81 Million
Contract Value $250 Million
Contract Term 20 Years
Contract Counterparties Azurix (American Water)